Verizon closeout checklist

Crown Envelope Adj Measurements

The photos a crew has to come back with on a Crown Envelope Adj Measurements scope, organized by section, with the note that tells them what to capture.

Sections
4
Photo requirements
18
Carrier
Verizon

Alpha Sector

  1. 1

    Alpha Highest Appurtenance

    Laser Measurement to Top of Equipment or Steel

  2. 2

    Alpha Lowest Appurtenance

    Laser Measurement to Bottom of Equipment ,Steel or Jumper Drip Loop

  3. 3

    Alpha Sector TOP Overall

    Clear Picture from Behind the Sector Showing NO Equipment or Steel Higher than previously measured HA

  4. 4

    Alpha Sector Bottom Overall

    Clear Picture from Behind the Sector Showing NO Equipment, Steel or Jumpers Lower than previously measured LA

  5. 5

    Alpha Pipe Post Adjustment Length Measurement

    Pipe total Length if adjustment had been made

Beta Sector

  1. 1

    Beta Highest Appurtenance

    Laser Measurement to Top of Equipment or Steel

  2. 2

    Beta Lowest Appurtenance

    Laser Measurement to Bottom of Equipment ,Steel or Jumper Drip Loop

  3. 3

    Beta Sector TOP Overall

    Clear Picture from Behind the Sector Showing NO Equipment or Steel Higher than previously measured HA

  4. 4

    Beta Sector Bottom Overall

    Clear Picture from Behind the Sector Showing NO Equipment, Steel or Jumpers Lower than previously measured LA

  5. 5

    Beta Pipe Post Adjustment Length Measurement

    Pipe total Length if adjustment had been made

Gamma Sector

  1. 1

    Gamma Highest Appurtenance

    Laser Measurement to Top of Equipment or Steel

  2. 2

    Gamma Lowest Appurtenance

    Laser Measurement to Bottom of Equipment ,Steel or Jumper Drip Loop

  3. 3

    Gamma Sector TOP Overall

    Clear Picture from Behind the Sector Showing NO Equipment or Steel Higher than previously measured HA

  4. 4

    Gamma Sector Bottom Overall

    Clear Picture from Behind the Sector Showing NO Equipment, Steel or Jumpers Lower than previously measured LA

  5. 5

    Gamma Pipe Post Adjustment Length Measurement

    Pipe total Length if adjustment had been made

Tower Top

  1. 1

    Tower Top

    Laser measurement of Top of Tower Steel

  2. 2

    Beacon Height

    Laser measurement of Height of Beacon

  3. 3

    Lighting Rod

    Tape Measurement from Tower Top to END of Rod

Run this on a real job

In Mastlens this checklist becomes a live job: the crew shoots each photo against its field on a phone, GPS- and time-stamped, offline if the site has no signal, and the finished closeout package builds itself.